Prince Mohammed Bin Abdulaziz International Airport Fuel Hydrant System Works

The project including facilities capable of simultaneously supplying jet fuel to 16 bridges (38 hydrant pits) and 20 parking aircrafts (54 hydrant pits) at Medina-Prince Mohammed Bin Abdulaziz International Airport Fuel Hydrant System agreementis signed in April 2013. Project will be completed in May 2014. The projectscope is:
- Procurement and installation of 5.448m 20”, 7.080m 16”, 654m 6” jet fuel pipelines (100% radiographically controlled),
- Procurement and installation of 92 Fuel Hydrant Pits and 30 High/Low Point Pits,
- Installation of 22 pcs 20” and 16” Double Block Bleed Valves (DBBV) with the necessary piping works and instruments in 6 Valve Vaults for Leak Detection System (LDS) and Emergency Shutdown System (ESD).
- Installation of the cathodic protection systems operated from an electronic paneland use sacrificial anodes.

Field of Activities