The manufacturing and erection of 11 pipelines (totally 24.200m) through thedistance of 2.200m between the jetty and Filling and Storage Plant of OPETPetroleum Co. with a capacity of 459.000m³ in Marmara Ereğlisi-Tekirdağ werecompleted in the following stages:
- Each line (10 PE coated steel pipes between 24” and 8” and 1 each DN355 PEpipe) were manufactured and mounted within a preconstructed 1.300m concretechannel onto the installed steel supports and within a 900m new trench of 9mwidth.
- After completion of welding works, welded areas were sand blasted for Sa2½grade of cleanliness and then wrapped with insulation bands.
- After insulation of the lines, the surfaces were checked for pinholes by using17.500 Volts Holiday detector and the defected areas were repaired.
- Mounted pipelines were controlled by hydrostatic test at 30bar and then coveredby sand.