İzmir Adnan Menderes Airport Domestic and International Terminal Building Jet Fuel Hydrant System Construction

The project including facilities capable of simultaneously supplying jet fuel to 27 aero planes at Izmir Adnan Menderes Airport’s New International Flights Terminal was completed in 2006. The project involved: - Installation of 5.800m 14”, 2.950m 12”, 2.700m 6” jet fuel pipelines (100% radiographically controlled), - Installation of 57 aero plane jet fuel hydrants and cathodic protection system operated from an electronic panel, - New Airport Jet Fuel Pumping Station comprising; 2x1.800m³ jet fuel storage tanks, 5 pumps (total capacity of 985m³/h), 5 filter/separators, 5 valve chambers, control board room and panels, MCC system and pumping station including all kinds of energy supply for the system, - The system installed is serving 15 bridges and 12 parking aero planes, - The basic and detailed engineering were in the scope of the Project.